Sunday 18 September 2022

Weekly Road Report – West End Ward #dundeewestend


DUNDEE CITY COUNCIL - WEEKLY ROAD REPORT

REPORT FOR THE WEST END WARD - WEEK COMMENCING MONDAY 19 SEPTEMBER 2022

Miller’s Wynd – closed at its junction with Hawkhill for major construction works. Start date Monday 27 June for 6 months.

Hillcrest Road - closed at No 23 until 20 September for redevelopment works on existing house. Closures will be intermittent and each should last no more than several days.

City Road (Tullideph Place to Logie Street) – closed for up to 4 weeks for Scottish Water emergency works.

Cleghorn Street at junction of Rosebery Street – 4 way temporary traffic lights from Monday 5 September for 4 days for CityFibre work.

Milnbank Road at Forest Park Place – 3 way temporary traffic lights from Tuesday 6 September for 2 days for CityFibre work.

Milnbank Road between Bankmill Road and Rosefield Street – road closed from Thursday 8 September for 2 days for CityFibre work.

Easson’s Angle – road closed from Monday 12 September for 6 days for CityFibre work.

Lochee Road - pedestrian lights and road narrowing from Monday 12 September for 4 days for CityFibre work.

Rosebery Street – 2 way temporary traffic lights from Monday 12 September for 5 days for CityFibre work.

Polepark Road – closed from its junction with Lochee Road to its junction with Milnbank Road (in a southerly direction only) for footway resurfacing works commencing Tuesday 20 September for 2 weeks.

Fyffe Street – temporary traffic lights from Tuesday 20 September for 3 days for CityFibre work.

Blackness Road (at Marchfield Road) – temporary traffic lights Wednesday 21 September for loop cutting work.

Blackness Road (at Jedburgh Road) – temporary traffic lights Thursday 22 to Wednesday 30 September for Scottish Water work.

Forthcoming Roadworks

Hillside Road (junction with Hillside place) – closed from Monday 26 September for 3 days for carriageway resurfacing works.

Lochee Road at Polepark Road - temporary traffic lights from Wednesday 28 September for 3 days for CityFibre work.

Park Street and Ash Lane – lane closure / road closure from Monday 3 October for 5 days for CityFibre work.

Lower Pleasance – road closure from Monday 10 October for 5 days for CityFibre work.

Nethergate (West Marketgait to Union Street) – closed from Monday 10 October for 9 days for carriageway resurfacing works.

Blackness Road (at junction with Balgay Road) - closed from Wednesday 19 October for 3 days to facilitate carriageway resurfacing works.