Saturday 1 April 2017

Weekly Road Report - West End Ward

DUNDEE CITY COUNCIL - WEEKLY ROAD REPORT

WEST END REPORT FOR SATURDAY 1 AND SUNDAY 2 APRIL 2017

Riverside Esplanade/Riverside Drive (Tay Road Bridge off ramp to 75m along Riverside Drive) – westbound nearside lane closure from Sunday 2 April for 33 weeks to facilitate V&A construction works.

REPORT FOR WEST END WARD WEEK COMMENCING MONDAY 3 APRIL 2017

SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street for 4 months.

Blackness Road/Glamis Road – temporary traffic lights for 2 weeks for gas main renewal.

Brown Street (Guthrie Street for 35m south) – closed southbound from Monday 3 April for 5 working days for Scottish Water mains repair works.