DUNDEE CITY COUNCIL - WEEKLY ROAD REPORT
REPORT FOR WEST END WARD WEEK COMMENCING MONDAY 6 MARCH 2017
Perth Road (at Arnhall Drive) – temporary traffic lights for 3 weeks for gas main renewal.
Blackness Road (at Rosefield Street) – temporary traffic lights for one week for Scottish Water mains renewal.
Nethergate (West Marketgait to South Tay Street) - closed for 2 weeks for carriageway resurfacing works.
SSE Glenagnes Cable Renewal – Lochee Road lane restrictions and closures on Blinshall Street, Fleuchar Street and Scott Street from Monday 6 March for 5 months.
Nethergate (at West Marketgait) – closed off-peak (9.30 – 3.30pm) on Thursday 9 and Friday 10 March for cycling works.
Perth Road (at Springfield) – temporary traffic lights for 2 weeks for footway works.